Canal Knowledge: The Fall and Rise of Surrey Canal Road Station

For ten years, Surrey Canal Road has been a modern ghost station. An empty station box beneath on the East London Line the only hint of its near existence. As TfL submit planning permission to build it, we look at how it never came to pass and why its time has finally come.

In late 2008, TfL had a problem. Plans for Phase 2 of the East London Line Extension (ELLX2 to its friends) were advancing. This would see the East London Line extended from Surrey Quays to Clapham Junction, connecting it with the South London Line on the way. This was a vital part of TfL’s strategy to complete the circle and create the full, orbital London Overground network that exists today. Changes in the available funding packages, however, had caused an issue:

They didn’t have enough money to complete the project.

TfL turned to the DfT and asked for an alteration to the plans on which their funding had been based. £24m had been earmarked in these to provide a Victoria – Bellingham service from 2012 onwards (which would replace the expiring South London Line). TfL asked that this be allocated instead towards funding ELLX2.

The DfT agreed to TfL’s request, but with conditions. The first of those is the cause of a zonal oddity that remains to this day: The DfT requested that to boost income Shoreditch High Street Station, then under construction, be placed in Zone 1 not Zone 2.

The second condition would cause several years of wrangling, followed by ten years of limbo: The DfT asked that TfL re-examine the case for an Overground station at Surrey Canal Road.

The Surrey Canal Triangle

The Surrey Canal Triangle

The site of Surrey Canal Road station sits in Lewisham, but its potential impact stretches beyond just that Borough. This is because the potential for urban renewal in this particular area of South London has long been recognised. Since 2011 (remember this year. It’ll come up again) the area has been a key part of the Lewisham Core Strategy. It’s been on the Mayoral radar for development just as long, and is currently part of the Lewisham, Catford, and New Bermondsey Opportunity Area within the 2021 London Plan.

This potential for development had been one of the reasons why a station on the Surrey Canal Road had featured in early plans for the ELLX2 project. Indeed that it be investigated for development had been a condition of Lewisham Council’s backing of the project. By the time that ELLX2 plans had been firmed up, however, the conclusion on TfL’s part had been that the Benefit Cost Ratio (BCR) of building it was good, but not as good as various other stations on the line. This meant that when funding became tight for the project in general, Surrey Canal was the low hanging fruit that had to go.

Enter the DfT

The DfT’s request for TfL to reconsider this decision in 2009 put the cat among the pigeons. Not because of the request for TfL to consider building it again – this was, ultimately, a station that TfL had wanted to build – but because the DfT also included a sweetener: if the station was included in the ELLX2 plans after all, then the DfT would eat £7m of the cost of building it.

This offer, understandably, changed the maths of the situation. TfL still had no money to commit to the station itself, but it now began scoping what the full cost of building one might be. This was carried out with a certain amount of urgency, because there is one universal truth to railway construction: once work begins, the cost of changing your plans soars. And construction of the ELLX2 was very close to beginning.

The result of this extra work was the conclusion that it was now economically viable to build the station. But more than £7m would be required. In fact, TfL costed the station (including box work beneath the line) at £10m, excluding risk. That left a £3m initial funding gap, which TfL still couldn’t find the funds to cover, and the question of who would accept the project risk.

With no development in the area sufficiently advanced to contribute (either voluntarily or as part of a compulsory planning obligation), the list of potential additional backers was really down to just one: The London Borough of Lewisham. Lewisham council were keen to do so, but finding the money from their own budget took time.

Time remained critical. TfL wanted to complete ELLX2 in time for the 2012 Paralympics (although it would ultimately not complete until December 2012). That meant construction had to begin by autumn 2010. As a way to get the station funding package over the line, TfL made Lewisham an unusual offer: they would loan the Borough £3m, interest free, which would be used to cover the remaining cost of constructing Surrey Canal Road. This creative solution would take advantage of both authority’s strengths: TfL had the “cash in hand” to cover the construction, they just needed a guaranteed way to get that money back in order to balance future books and expenditure. The question of risk remained, but both parties were confident an agreement on that issue could be found.

In January 2010, Lewisham finally found a way to provide the loan payments that would be required to meet their end of the bargain. The solution was pretty innovative. Changes to the way Local Investment Plan funding was being allocated across London meant that the Borough was about to receive an unexpected boost to its allocation, which would rise from £2.4m, to £2.9m from 2011 onwards. As this funding was new and unallocated, Lewisham agreed that the increase would be paid straight to TfL until the transport authority had received either £3m, or the full cost of the station (including risk) – whichever was higher.

Just in time, a funding solution had been found. Surrey Canal Road station could go ahead.

Or so TfL and Lewisham thought.

Enter the DfT. Again.

The final arrangements between TfL and Lewisham were signed off in March 2010. TfL then turned to the DfT and requested that they officially be granted the £7m that the DfT had indicated that they would commit to building Surrey Canal Road station.

The DfT informed TfL that, unfortunately, their £7m commitment to the project had technically expired in March 2009. This wasn’t news to both TfL and Lewisham. What had become clear early on in negotiations, however, was that both authorities would require time to innovate their way to a solution for the funding gap. When the deal expired, TfL and Lewisham thus both sought assurances that it was worth them continuing to try and find a way to meet the extra cost. In response, the DfT had indicated that they recognised this would take time and that the money would be left unofficially on the table, as long as the result of the TfL and Lewisham negotiations saw the project overrun risk sit with those two authorities, with no obligations on the DfT. Indeed finding a way to do this had been a significant part of the delay.

The DfT’s stance, however, had now changed.

TfL and Lewisham’s request for the renewal of the £7m guarantee for station construction was initially greeted with the ministerial equivalent of radio silence. Then, subject to questioning and letters from the Greater London Authority (GLA), the DfT confirmed that whilst in principle they weren’t against meeting their previous commitment, they intended to run their own value-for-money assessment of the station first.

Exit the DfT

With the date of construction of ELLX2 looming ever closer, TfL, GLA and Lewisham all continued to push the DfT for a firm funding commitment. In September 2010, just as construction was finally beginning, the answer finally came.

In response to a letter from Caroline Pidgeon AM, Transport Minister Theresa Villiers gave the DfT’s answer:

Given the current financial constraints under which the Department is operating, the lack of certainty regarding the redevelopment of the area and the relatively weak business case for the scheme even with the development in place, I have concluded that we cannot provide the £7m support required to build [Surrey Canal Road] station.

Theresa villiers, letter to caroline pidgeon am

Passive Provision is maintained

There was no time to find an alternate source of funding, but TfL and Lewisham were at least able to agree (and fund) one thing: passive provision was built into the bridge at Surrey Canal Road for a future station at that site. This is why, today, a large empty space exists beneath one side of the bridge, and why the support structure and pilings at that location are reinforced. Surrey Canal Road became a modern ghost station. Rather than being the ghost of station past, it was instead the ghost of a station yet to come.

Passive provision represented a frustrating failure for those who’d pushed hard to see the station come to pass, but it at least ensured their remained hope for a station at that location in future. It did this by ensuring that as much of the heavy infrastructure work required for a station build as possible was carried out as part of the ELLX2 project. This avoided, as much as possible, excessive costs for turning the site into a station in future through requirements for extensive line closures or structural reworking.

The space under Surrey Canal Bridge

Enter New Bermondsey

In 2011, it seemed that a use for that passive provisioning might come sooner than everyone expected, albeit with a rename. Lewisham Council had granted outline planning permission for developer Renewal’s proposed £850m housing and retail development on the Surrey Canal Triangle site. As part of this, the package of transport improvements mandated included contributory funding for Surrey Canal Road Station.

Renewal’s plans for the area would, however, prove to be drawn out and controversial. It wouldn’t be until 2014 that firm agreement on just how a station might manifest at the site seemed to firm up. These included a request from the developer (agreed to by TfL) that the station be named New Bermondsey instead, in reference to the development area that Renewal were looking to create.

As was proving to be a habit with the Surrey Canal Road site, however, these plans would stall and ultimately fall through.

Third time lucky?

This brings us, finally, to the situation today. Over time, the need for the station has increased rather than decreased, as reflected by the area’s importance in the 2021 London Plan. So it is no surprise, perhaps, that TfL have continued to look for funding opportunities for a station on the site from elsewhere.

And funding they have now finally secured – via the Government’s Housing Infrastructure Fund. With £10m (plus inflationary costs) committed from there, they have submitted a planning request to Lewisham for permission to finally build the station, now known simply as “Surrey Canal”.

That planning application is required because the previous planning permission for a station at the site didn’t include provision for structures more than 5m above track level. This is actually good news for both future passengers and readers of LR. For passengers, it’s because of the reason why that 5m rule will be broken: the plan includes provision for the station to receive full-sized lifts to both platforms (although whether these will be available at opening is unclear). It also includes covered platforms as guaranteed. For readers, it means we get a very early (but indicative) look at what the station layout will be and how it will operate. You can read the full planning application on the Lewisham planning website, but the key highlights are:

  • Construction (subject to permission) will begin in February 2022, with a target December 2024 completion. This would likely mean an early 2025 opening.
  • Full lift provision is baked in UPDATE: TfL have confirmed lifts are in the plans from the beginning.
  • The addition of solar panels and a green roof to an extended platform roof.
  • UPDATE: TfL have confirmed staffing will be in line with other stations
  • There will be no pedestrian overbridge
  • The station will feature glass at ground level, with stainless steel mesh cladding running up the sides.
  • Cycle storage facilities will be provided.
  • There is a developer commitment to provide interchange at the station with two bus services (we assume that one of these would likely be the 415, as this was part of the original 2011 plans).

Indeed broadly, in design the station arguably resembles a much-modernised version of the Overground station at St James Street in Walthamstow, although one hopes (and assumes) that it will lack the eight inch gap between train and platform that can be found at points there.

Front elevation designs. Note the triple entrance and stainless steel sides
Platform roofs. note the ‘green walling’ and solar panel provision
PLATFORM LAYOUT. NOTE LIFT POSITIONS, SEATING PROVISION AND EMERGENCY STAIRS
Elevation and platform layout. note the ‘provision’ for lifts
InDICATIVE CGI PROJECTION OF THE STATION

The end of the beginning?

With funding finally secured, plans submitted and provisional dates of construction in the calendar, it seems that Lewisham will finally get the extra Overground station it wanted from the beginning. If so, this will be good news for those living in the area (and for those travelling to watch Millwall play).

Given the history of the site, however, it is perhaps worth not quite uncorking the champagne just yet. The story of Surrey Canal has been a complex one, and there may be more twists and turns lurking yet…

London Reconnections is entirely supported by its community. If you like what we write and what we share, then please consider joining our Patreon. Every little helps!

UPDATE 27/11/2021

TfL have now provided us with an official statement, which is reprinted below:

Alexandra Batey, TfL’s Director of Investment Delivery Planning, said: “We’ve made some updates to previously agreed plans from 2011 to ensure the proposed Surrey Canal station meets  the latest technical standards and requirements.  This includes updating the station’s step-free proposals along with the potential provision for longer five-car trains and changes to signals for better driver visibility.  Although design work is underway for the station, further operational assessments, designs and costs will need to be considered before a decision can be made on whether we can proceed.”

Notes to editors:

  • Subject to funding and other conditions, the new station on this London Overground route could be in place by the mid-2020s.
  • The new station would provide new public transport for existing residents and businesses and serve over 5000 new homes planned along with a wide range of  new commercial and community and leisure space.
  • Initial planning permission was granted in 2011 under a previous Transport and Works Act Order when the East London line was upgraded.  These plans were for an outline design with this latest update providing more detail including the need to building any station slightly higher.
  • The design and development work on this project is being funded by the Department for Levelling Up, Housing and Communities ‘Housing Infrastructure Fund’, which is subject to certain conditions

29 comments

  1. The unstaffed nature of the station is fairly eye-opening. Overground was originally going to be unstaffed but this changed under Mayor Ken with the Standard ran its campaign.

    I wonder if the the RMT has spotted this yet?

  2. That and the lifts are the two questions I’ve pinged at TfL for confirmation on.

    The way the planning application is written definitely suggests unstaffed, and this was the original plan for the station back in 2010 as well for cost-saving reasons.

    Hopefully they’ll be able to confirm their current plans though.

  3. I’d abandoned the idea of this as a route to The Den and switched my hopes to the Bakerloo extension although it looks as if I’ll be sticking with the 1 to Surrey Quays for a while.

  4. The idea of the station being planned as unstaffed leads me to think of four possible scenarios.
     
    1) This is simply an administrative error and it is not intended.
     
    2) This is intended to get a staffed station eventually but it is easier to make a case for an unstaffed station and then subsequently staff it. Presumably it will never have a ticket office.
     
    3) A precedent has been set with Emerson Park for the occasional unstaffed station on London Underground and it makes sense for it to be unstaffed – at least initially when demand is unknown and maybe really low. Exceptionally, level access from platform to train could be possible here so this would be no worse than a DLR station when it comes to access for all.
     
    4) This is the start of a plan to remove staff from many London Overground stations. It is hard to see this happening with a commitment to to access for all and a near-total commitment for London Overground stations to be staffed from the first train to the last train.
     
    I suspect either options 2) or 3) are intended.

  5. Agreed. I do think 1) is possible as well though, and may just be a quirk of how the planning doc has to be worded. I’ve pinged TfL a query, which should clear it up hopefully.

  6. Others with a better understanding of the planning system may have an opinion on this.
    https://assets.savills.com/properties/1E3B8788-1E23-4934-B15B-4CC8360153C6/Leathams,%20227-255%20Ilderton%20Road%20APPROVED.pdf
    A warehouse site, 400 metres from the proposed station, has been recently decommissioned and is now for sale. It has already been re-zoned for housing, with permission granted for a high/dense development. The brochure includes a strong pitch about the proximity to the new station. The brochure also shows a stipulation that the developer will contribute to CIL funds, but as it is located in Southwark rather than Lewisham I’m not sure if these funds can/will be allocated to the development of the new station.
    Of tangential interest. The permission for this development includes zero car parking provision, and a restriction preventing the granting of street parking permits. Such a restriction has been common in the “skyscraper zone” of the Isle of Dogs for many years but I suspect is a fairly novel stipulation in other boroughs.
    This area around the proposed station site is one of the few (possibly the only?) remaining areas in inner London that does not currently have resident parking restriction. I expect that will change as soon as development gets underway.

  7. Island Dweller

    Of tangential interest. The permission for this development includes zero car parking provision, and a restriction preventing the granting of street parking permits. […] I suspect is a fairly novel stipulation in other boroughs.

    At the risk of continuing on something tangental, Croydon has even stipulated that should a particular development go ahead and subsequently a restricted parking zone be introduced at some point in the future, the residents would not be entitled to a street parking permit.

  8. Good news: TfL have confirmed the lifts are baked from the start. And so is staffing the station. It’s an admin thing with the planning doc.

    Have updated the article.

  9. I didn’t realise the Shoreditch High Street Zone 1 thing was linked to this – I’d always assumed it was DfT saying something like “you need £x ticket revenue from the project for us to be happy, and therefore we need it to be a Zone 1 station”.

    (off topic, but I assume it TfL like the extra income too much to change it to a Zone 2 station!)

  10. Possibly relevant?
    So, Surrey Canal (road) is to open, largely because of new housing in the area.
    Whereas, only a few weeks ago, A proposed-to-be-paid-for-by developers station, on the N side of the Thames has been firmly squashed, apparently by DfT. This was to have been at “Beam Park” on the Tilbury loop.
    Not what you would call a consistent approach, is it?
    Is there any more recent information on this latter proposal & rejection?

  11. The important difference between Surrey Canal and Beam Park is that – as noted in the article – the hard work for Surrey Canal has already been done. Building the station won’t require heavy engineering or line closures, and therefore the DfT isn’t worried about being stuck with overruns or liability. For Beam Park, this is not the case.

  12. Greg T – see the local newspaper for recent news:-
    https://www.romfordrecorder.co.uk/news/housing/beam-park-buyers-consider-legal-action-over-station-8493398

    There are those who claim that in the last year or two national support for, and funds for, such projects have been tainted by reference to the local MP’s party label. In this instance, the situation is given extra mystery in that the relevant local authority (LB Havering) is run by a different party (i.e. not the MP’s), and what about the former mayor’s advocacy for Beam Park when he was in City Hall, mentioned in this article, before moving back to Westminster, leaving GLA/TFL in the hands of his political opponents?

  13. @Twopenny Tube

    I thought that the main problem for Beam Park station is that there isn’t enough of an existing C2C service – it’s two an hour – running though the station to make it a worthwhile “turn up and go” service pattern?

    Given that the C2C line is the only 100% segregated train network in London vicinity, it would require a lot of extra work to bring the perhaps more useful Barking -> Upminster trains to Beam Park. However they are going to be sent to Barking Riverside very soon.

  14. I thought that there was still no change from the ongoing contract with Arriva Rail London to provide

    ” All stations will continue to be staffed from 15 minutes before the first train of the day until 15 minutes after the last – a continuing commitment that makes London Overground stations stand out on the national rail network”

    The gates are automatic but usually a staff member is there on the gate-lane to provide assistance.

    I’m not sure why anything thinks this arrangement has changed.

  15. I’m not sure why staffing is still being discussed. TfL have now responded to this question and I both commented with their answer and updated the article:

    The station will be staffed if built. It’s just a quirk of the way the planning document is written.

  16. @Pedantic @John Bull
    Re:Staffing precedent at Emerson Park
    Does this expectation of continual staffing only apply to London Overground? When I lived close to Westbourne Park station a few years ago, it was routinely left unstaffed for the latter part of the day, and even then it had a more frequent service than most parts of LO.

  17. @Paul

    That’s correct. It applies to London Overground only, not to the Underground which often has stations with open gates during the day, especially outside Zone 1. The District Line often has open gates and no staff present east of West Ham. This is often a great source of material for that TV show that follows the TfL Revenue Protection people!

    See also the TfL DLR, 90% of which are unmanned because their are PSAs on the trains. The only DLR stations that are staffed are those that interchanges with other services enough to have gate-lines (Stratford, West Ham, Canning Town, Woolwich Arsenal and Bank).

    I guess you must count London Trams as being staffed

  18. Pedant moment. It’s not just DLR interchange stations that are staffed. Safety requirements mean stations in tunnel have to be staffed, so Island Gardens and Cutty Sark too.

  19. I still see this as a missed opportunity to build an interconnect station between the various lines running within the triangle especially between the ELL and the slow/metro services into LB from the Deptford direction.

  20. Is there any update on why building has not begun as planned in February 2022?

  21. I second that Karer. Significant number of new builds have are being constructed or close to completion on Ilderton Road and I have not heard a thing about when construction will actually start at Surrey Canal. @John Bull, do you have any further knowledge on this? Or is it doomed again?

  22. @ John Bull. Is there an update on this? Has construction started or is it doomed again?

  23. Construction certainly didn’t look to have started when I took the train from Canada Water to Denmark Hill last weekend.

  24. The station’s on hold (perhaps for a long time) due to construction cost inflation

  25. 70 years ago l worked on the motive power of BR north London rail at
    Devons Rd , Bow the line used to serve
    Poplar Docks via some derelict stations . The Depo was adjacent to the Lime House Cut canal.
    Has the line been lifted or is it still in use? I jUst wondered if the poplar docks has been redeveloped?

Comments are closed.