In part 3 of our look at the plans for Bank station we described the continuing growth that is taking place there and the revised plans to handle this growth, including a work site at …
Continue readingAuthor: Pedantic of Purley
Bank Station Part 3: A Dance of Dragados
As regular readers will know there was a consultation exhibition about the Bank Station Capacity Upgrade recently. Long term readers will also recall that there had been at least one previous consultation which took place …
Continue readingThe new Walbrook entrance at Bank
Recently there was an exhibition about the updated proposals to greatly enhance Bank station capacity, a scheme that should be completed in 2021 if all goes according to plan. As a result of those proposals, …
Continue readingPaddington: Bearer of Many Names
In part 2 of Uncircling the Circle we rather skipped over the issue of changing trains at Paddington. This issue was picked up by some readers who pointed out that, once Paddington (Hammersmith & City) …
Continue readingUncircling the Circle: Part 2
In part one of Uncircling the Circle we described how London Underground and its predecessors had tried, unsuccessfully, to eliminate the Circle Line as a continuous circle from the underground system. We also looked at …
Continue readingUncircling The Circle: part 1
In part 2 of The Past, Present and Future of Metropolitan Line Services we finished with details of frequencies for the Metropolitan Line once the Sub-Surface Lines upgrade was complete. With plans for a overview …
Continue readingSecond Second Tuesday meeting
Just the briefest of reminders that we will have our next pub meeting on Tuesday 8th October from 6 o’clock onwards. Same details as last time. Click “Continue reading” for link to details of the …
Continue readingSecond Tuesday Meeting
Just a quick reminder to those interested. We intend to meet monthly for a drink and a chat at the Rose & Crown in Southwark on the second Tuesday of each month. This is the …
Continue readingThe Past, Present and Future of Metropolitan Line Services: Part 2
In part 1 we looked at the service that had historically run on the Metropolitan Line, since its takeover by the London Passenger Transport board. Major improvements to both track and service occurred in the …
Continue readingThe Past, Present and Future of Metropolitan Line Services: Part 1
We reported last month that the Croxley Rail Link (CRL) scheme had been given the go-ahead, with the Transport and Works Act Order reported to be approved by the Secretary of State for Transport. Since …
Continue readingThe TfL Olympic Legacy: Measuring the Unmeasurable
It has probably not escaped your notice that around a year ago a big sporting event was staged and was largely based in London. In the build-up and follow-on one of the words most associated …
Continue readingThameslink and the NAO: part 3: All’s well that ends well?
This article, following on from part 1 and part 2 of articles on the report from the National Audit Office (NAO), was intended to be very short and mainly deal with the limited NAO comments …
Continue readingThameslink and the NAO: Part 2 – Wherefore Art Thou Siemens Rolling Stock?
In part one we looked at the verdict of the National Audit Office report on Thameslink and more specifically on the infrastructure work done so far. In part two we look in detail at the …
Continue readingThameslink and the National Audit Office: Part 1
It is the same old story. We were planning on giving articles about Thameslink a break and then something else comes along. This time it is a report from the National Audit Office (NAO). This …
Continue readingNorthern Line Postscript: Deep In The Heart Of Camden
Our recent article on future Northern Line upgrades was not really meant to be about one particular aspect but how the pieces as a whole fitted together. It was acknowledged in the title that the …