A Look at the Crossrail Tunnelling Portal at Royal Oak

Sandwiched between the Westway and the Hammersmith & City Line is Crossrail’s Royal Oak Portal – the point from which central section tunnelling will start in the west and the point at which trains will enter or leave the tunnelled section.

Construction of the Portal has now largely been completed, with tunnelling due to commence next year. At only 21m wide, its an incredibly narrow worksite and, as the photo below demonstrates, one that borders pretty much directly onto the live railway at various points.

A Circle Service Thunders Past

A Circle service thunders past

For those familiar with this particular stretch of the Hammersmith & City, the site took over (amongst other things) the site formerly occupied by the old black cab park (complete with café and petrol pumps). All of that, and more, has long since disappeared beneath the site approach.

Looking towards Royal Oak Station

Looking towards Royal Oak Station

The Remains of the Arches

The Remains of the Arches

Spoil work continues as an FGW service approaches Paddington

Spoil work continues as an FGW service approaches Paddington

Beneath the Westway

Beneath the Westway

Advancing towards the Portal itself presents a rare opportunity to see Royal Oak from its northern side.

Royal Oak from the north

Royal Oak from the north

Royal Oak close up

Royal Oak close up

Hampden Street footbridge sits at the start of the 285m long ramp down to the Tunnel Eyes. This was raised during an Easter blockage to facilitate the works beneath it, and the evidence of that can be seen on the second photo below. It will, however, still need to be lifted twice once the TBMs are assembled, in order to allow them to pass beneath.

The Hampden Street footbridge

The Hampden Street footbridge

The additional height added to the Hampden Street footbridge

The additional height added to the Hampden Street footbridge

The area cleared for TBM assembly is also where the new turnback sidings will ultimately be located. This can be seen in the photo below. First Group’s buses will need to be moved off the rear of the site to Atlas Road until after construction is complete. These will ultimately return to new facilities on top of the sidings at the end of the project.

Interestingly – especially in the context of Kensington & Chelsea’s push for a Crossrail station at Royal Oak – talking to the contractors on site revealed that the siding platforms that featured on the original plans will now not be built. Unfortunately they were unable to confirm when this decision was made.

The Siding site

The siding site

The Portal itself has elements of the Death Star trench about it when viewed from the surface. Approximately 100m of Sheet Pile Wall gives way to another 190m of D-Wall as the retained cutting gets deeper. Temporary props are still in place at the Tunnel Eye end, marking the point at which the evacuation stairway will eventually be sited.

The view from the side of the Portal

The view from the side of the Portal

Temporary Props over the Tunnel Eye

Temporary Props over the Tunnel Eyes

Heading into the Portal itself, a base slab on which the trackbed will eventually be placed gently slopes down to the Tunnel Eyes. A number of Permanent Props are in place towards the end, strangely reminiscient of the Connaught Tunnel (although more utilitarian in design).

Looking back up as the ramp begins its descent

Looking back up as the ramp begins its descent

The cutting deepens

The cutting deepens

Looking towards the Tunnel Eyes

Looking towards the Tunnel Eyes

The Permanent Props cast shadows over the proceedings

The Permanent Props cast shadows over the proceedings

The cutting (with help from Matt from Sian Formwork in the Cherry)

The cutting (with help from Matt from Sian Formwork in the Cherry)

The Tunnel Eyes from above (again, with thanks to Matt)

The Tunnel Eyes from above (again, with thanks to Matt)

The Tunnel Eyes themselves have a diameter of 7.24m and sit in front of the tunnel head. It’s these the TBMs will use to drive off from when they begin tunnelling. Looking inside, they actually gently angle outwards, reflecting the fact that the twin tunnels will bow out slightly beneath Paddington.

Work continues at the Tunnel Eyes

Work continues at the Tunnel Eyes

The Tunnel Eyes up close

The Tunnel Eyes up close

Looking back from the Eyes gives an idea of the track level

Looking back from the Eyes gives an idea of the track level

Overall, its an interesting and compact site, but one that will shortly be a hive of activity. Once the TBMs arrive and tunnelling begins, we will endeavour to engineer a return – something that would likely produce a very different set of photos.

2 comments

  1. It’s such a shame that the reconstructed Hampden street footbridge pays no regard to the safety of its many users and has created a muggers paradise with no views in, out or around blind corners and no cctv. Most people will be too scared to use this / terrified of they choose to use it during the daytime let alone at night

  2. Great work happening at Royal Oak Portal. The Crossrail team and their project staff have done a fantastic job!

Comments are closed.